W. Rosemary St. Weekly Update: Friday, November 13

 

This project is 80% complete. Weather and other unforeseen factors could impact the pace of this project. Over the next month, work will alternate between Phases 3, 4, and 5.

Please note: This is an 18-month project, on track to be complete by Spring 2027. The percentage complete is updated monthly.

Next week, on Monday, November 16, through Wednesday, November 18, Moffat will prepare the Phase 3 area (Mitchell Lane to Andrews Lane) for permanent asphalt paving. Please note, permanent asphalt is not final asphalt paving. Crews will also conduct purity sampling of the newly installed water main within Phase 4 (Andrews Lane to Church Street). In addition, crews will work to complete installation of the new water main within Phase 5 (Church Street to Pritchard Avenue).

On Thursday, November 19 and Friday, November 20, crews will connect customers within Phase 4 (Andrews Lane to Church Street) to the newly installed water main, pending purity sampling results.

Residents and businesses should contact Project Superintendent Melecio Cedillo at 919-819-8922 if they have any questions or concerns about accessing their residence or business. All efforts will be made on site to provide access to those residing and working within the active construction area.

WATER SERVICE IMPACTS: November 19-20: Pending purity sampling results, a 30-45 minute water service disruption for customers within Phase 4 (Andrews Lane to Church Street). Impacted customers will be notified in advance of this service disruption.

TRAFFIC IMPACTS: November 16-18: Mitchell Lane to Pritchard Avenue closed to through traffic. Through traffic will be detoured to W. Franklin Street.

November 16-17: Single-lane closures from Andrews Lane to Church Street. Through traffic will be maintained.

November 19: W. Rosemary Street/Church Street intersection closed from W. Franklin Street approach.

November 19-20: Andrews Lane to Church Street closed to through traffic. Through traffic will be detoured to W. Franklin Street.

The bike lane on W. Rosemary Street from N. Merritt Mill Road to Andrews Lane will remain closed. Cyclists are asked to share the road with motorists in this area.

Click HERE to sign up for our contact list to receive weekly updates on the W. Rosemary St. Water Main Replacement Project.

Project Details

This project will replace 3,540 linear feet of the existing water main with ductile iron pipe, and 440 linear feet will be replaced with PVC pipe. Construction will be phased, so customers will experience minimal impacts while construction is outside of their immediate area.

Community Meetings

PAST

Tuesday, September 30

Hargraves Community Center
6:30-7:30 p.m.

Meeting Summary: Community property managers, business owners, and town and residents, and representatives from organizations on or near the project site participated in the September 30 community meeting about the W. Rosemary Street Water Main Replacement Project. OWASA staff along with engineering consultants supporting the project presented how the project will be carried out in eight sections, plus traffic detours, parking impacts, pedestrian access, and water service impacts during construction.  Click here to view or download a full summary of the September 30 community meeting.

Wednesday, June 18

Chapel Hill Public Library, Meeting Room A
2:00-3:00

Meeting Summary: Over 20 community property managers, business owners, and town and county officials participated in the June 18 community meeting about the W. Rosemary Street Water Main Replacement Project. This meeting focused on the direct impact to residents and businesses adjacent to the construction area. OWASA staff along with engineering consultants supporting the project, answered questions about how the project will impact traffic, parking, access to businesses, and water services during construction.  Click here to view or download a full summary of the June 18 community meeting

Location and Timeline

Construction began to replace the water main from N. Merritt Mill Road to N. Columbia Street in fall 2025. We expect construction to last about 18 months total.


This map shows the extent of the project. The work is being completed in sections over the course of 18 months.

 


This map shows parking near the project sites. OWASA is working with the Town of Chapel Hill to offer parking to mitigate any lost parking access during construction.

Questions or Concerns?

For more information on this project, please contact project manager Darren Berger at dberger@owasa.org.