Community Meetings

We will host community meetings in fall-winter 2024-25 to discuss the project and prepre customers in the area for the expected construction impacts. Keep an eye on our website and your email inbox for event details.

Location and Timeline

Construction will begin to replace the water main from N. Merrit Mill to N. Columbia in July 2025. We expect construction to take one year.

Details

This project will replace 3,100 linear feet of the existing water main with ductile iron pipe, and 440 linear feet will be replaced with PVC pipe. Construction will be phased, so customers will experience minimal impacts while the construction phase is outside of their immediate area.

Questions or Concerns?

For more information on this project, please contact project manager Darren Berger at dberger@owasa.org.